AS OF DECEMBER 31, 2012 THE SOUTH-WEST LAKE MAXINKUCKEE SEWER SYSTEM IS SUBSTANTIALLY COMPLETE AND FUNCTIONING. WATCH HERE FOR AN UPDATE IN MARCH 2013! To: South […]
The District was confirmed as active with Indiana 811 locator services in late December of 2011. Call before you dig! Pumps were released for pick-up as […]
The following is a summary of the costs involved in the project. It may explain some of your questions. ___________________________________________ There are 3 buckets of costs […]
Each of you should have received an engineered drawing during December of 2010 or early January of 2011 showing the location of the hook-up point for […]